SPCT Container Terminal Dredging Plan & Environmental Safeguards
Background
SPCT Background Sparrows Point Container Terminal (SPCT) is a proposed 330-acre redevelopment project consisting of 165 acres for a new container terminal and intermodal yard, with an additional 165 acres for support facilities to enhance operations of the terminal. This joint venture between Tradepoint Atlantic and Terminal Investment Limited (TiL) represents a major growth opportunity for the State of Maryland that will solidify Baltimore as one of the most competitive ports on the east coast. The planned state of the art container terminal will expand the Baltimore service for MSC (Mediterranean Shipping Company, create thousands of jobs, and dramatically enhance and support the long-term growth of the Port of Baltimore and the State of Maryland.
Blended Approach
To accommodate modern container vessels, the existing Sparrows Point Channel that serves Tradepoint Atlantic’s terminals will need to be widened and deepened to -52ft. In doing so, 4.2 million cubic yards of channel material will need to be dredged and placed. A blended approach of several placement options has been identified.
- Ocean Placement
- Coal Pier Channel
- Upland Placement at Sparrows Point – High Head Industrial Impoundment
- Capacity at Existing Maryland Port Administration Dredge Material Containment Facility (DMCF)
USEPA Ocean Placement
- 1.57M CY of material meet the MPRSA criteria for ocean placement If selected as a preferred option, the USEPA must issue a formal concurrence that the material meets the Section 103 MPRSA requirements, and the USACE must issue a Section 103 permit prior to the transport and placement of material at the Norfolk Ocean Disposal Site (NODS), a USEPA designated facility.
Coal Pier Channel
- Potential capacity – 750,000 CY
- Naturally occurring containment area – uses existing native terrain and infrastructure
- Existing distressed waterway
- Very constructable
High Head Industrial Impoundment
- Industrial facility – used by Baltimore City for Back River Wastewater Treatment Plant to discharge industrial water
- Non-jurisdictional onsite placement within Sparrows Point and TPA property
- 1.25M CY of potential capacity in an upland facility to be built
- Will require construction of a berm wall and dikes
Use Of Existing Capacity At An Existing Maryland Port Administration Dredged Material Containment Facility
1.25M CY at either Cox Creek or Masonville DMCF Placement would occur over four years FY26 – FY29
Dredging Plan & Environmental Safeguards
SPCT developed a comprehensive Sampling and Analysis Plan, approved by the Maryland Department of the Environment (MDE), for the material to be dredged from SPCT – 4.2 million cubic yards of material associated with the project. The area is divided into 28 dredge units (DUs), with 97 discrete sample borings collected for testing (North Channel sampling shown in green to the right). Tradepoint Atlantic performed a first-ever risk assessment to ensure there are no unacceptable risks. SPCT will publicly share sediment testing data once the state and federal agencies complete their evaluations.
North Channel Plan & Analysis
- 13 dredging units (DUs) — 2.55 million cubic yards of material
- 52 locations were tested for upland material placement
- Bulk sediment testing was approved by the Maryland Department of Environment Vibracoring and sonic drilling to -52 ft. channel depth
- 292 different chemicals and compounds tested
South Channel Plan & Analysis
- 15 dredging units (DUs) — 1.65 million cubic yards of material
- 45 locations were tested for ocean/upland material placement
- Ocean sampling analysis plan approved by the Environmental Protection Agency / upland dredging sampling analysis plan approved by the Maryland Department of Environment
- Ocean Placement Evaluation Report available online at spctmd.com
- Vibracoring and sonic drilling to -52 ft. channel depth
- 292 different chemicals & compounds tested
Localized Impacts of Dredging
Today’s dredging methods are designed to minimize disturbance to the water column during dredging events. Presence of sediment material in the water column during dredging events is measured in what scientists call “Turbidity” (sediment material found within the water column during dredge). TPA studied the impact of dredging within the Sparrows Point Channel from prior dredge events and found that turbidity is fairly localized within TPA’s shoreline and the Sparrows Point Channel.
Environmental Compliance & Public Involvement
If the material is determined eligible for placement, a thorough public permitting process will be required and conducted. Required permits are listed below:
Tidal Wetlands License
- Required to dredge container terminal access channel for any dredge placement alternative
- Process includes application period, public notice, and public hearing – overseen and issued by MDE and Board of Public Works (BPW)
- Will require material analysis approval by MDE
- Will specify placement location (material must meet standards)
- Will specify seasonal prohibitions, as applicable
- Will require watertight barges and best management practices (e.g., environmental buckets)
Federal Permits
- Clean Water Section 404 Permit for activities performed in waters or wetlands of the US
- Mitigation is required to offset unavoidable impacts
Water Quality Certification
- Section 401 State Water Quality Certification from MDE for dredging activities
State Discharge Permit
- State Discharge Permit required for upland impoundment and coal pier placement
- Public hearing is likely required
- Tidal Wetlands License will be required
Water Appropriation and Use Permit
- Water Appropriation and Use Permit is required for dredging operations, specifically for creating a slurry to off-load dredge material, for dust control or to maintain water levels in ponds and wetlands
- Public hearing is likely required